JXSC has provided a successful 50TPH alluvial gold washing plant in Nigeria. We design the gold wash plant process flowchart & plant layout drawing according to ore conditions, provide a complete set of plant machines and send Chinese engineers to the mine site for plant installation & commissioning guidance.

Introduction

Minerals: Alluvial Gold
Capacity: 50 TPH

Process: The raw material is the alluvial gold with much sticky clay, which needs to wash clean. And the gold concentrate size is 0-6 mm.

Solutions & Process

Alluvial Gold Wash Plant With Sticky Clay

Nigeria 50TPH Mobile Alluvial Gold(With Clay) Washing Plant Flowchart
  1. Excavator feed materials to feeding grizzly hopper ,with 75mm gap,+75mm big waste stone are removed.
  2. Below 75mm materials to trommel scrubber, 2 layers screen, mesh size 6mm,20mm; versize 6-75mm are waste material.
  3. 0-6mm to centrifugal concentrator for recovery fine gold.
  4. Gold concentrates from centrifuge to shaking table. Tailings from centrifuge to sluice box for recovery gold tailings.
  5. Through smelting furnace make gold concentrates to gold bar.

Equipment Lists

  • Moible Trommel scrubber: JXSC-1200,1 set
  • Sluice box: 1*6m, 1 set
  • Gold Centrifugal concentrator: STLB60, 1set
  • Shaking table: 2100*1050mm, 1 set
  • Gold melting furnace: 1 set
  • Slurry pump 1set